SPC FLOOR Automatic Back Pad Laminating Machine Instruction Manual Book
Content:
- Introduction
- Main parameters
- Installation requirements
- Machine layout map
- Infeed conveyor
- Glue Spreader
- Passing Belt
- Laminating Machine with Auto Cutting System
- Passing Conveyor
- Roller Conveyor
- Trimming Machine
- Machine Pre- operation Guide and Main Points.
- Instruction Manual File
Introduction
SPC HF400 flooring automatic back pad laminating machine is specially designed to laminate the soft pad(IXPE) to the back side of the flooring , equipped with auto cutting system and side trimming system. Highly improving the working efficiency , saving label cost , reducing the soft pad(IXPE) waste.
The glue spreader is default designed to use the cold glue, mold temperature machine and glue melt machine are optional choice to heat the anilox roller in case the clients want to use hot melt glue.
The flooring is passing through the machine by the belt and rollers, then going to the glue spreader, lamented with the soft pad (IXPE) by rubber rollers, soft pad (IXPE) is cut by the high servo motor with high speed round knife. Extra soft pad (IXPE) will be shaved by the trimming system.
Main Parameters of SPC FLOOR Automatic Back Pad Laminating Machine
Available flooring length: 600~2000mm
Available flooring width: 80~400mm
Available flooring thickness: 80~400mm
Working speed max: 35 m/min
Total power: 16.8 KW
Mold temperature machine power: 17KW(optional choice)
Glue melt machine power: 6 KW(optional choice)
Installation Requirements:
- Tear off the protective film before installation.
- Check the machine situation ,including the glue tank, glue plate , tool box, user guide.
- Place the machine regarding to the layout map showing below.
Machine Layout Map
1. Infeed conveyor 2. Glue spreader 3.Passing belt 4. Laminating machine with auto cutting system 5. Passing conveyor 6 Roller conveyor 7. Trimming machine 8. Electrical control
Infeed Conveyor
1. Pressing roller 2. Guide liner 3. Dust remover 4. Infeed baffle 5. Limiting plate 6. Belt A. Sensor
- Adjusting the “2” regarding to the width of the flooring , make sure the flooring is at the middle of the belt.
- Adjusting the “3” height, the height is higher than single flooring’s thickness, but shorter than two flooring’s thickness, make sure only one piece of the flooring pass through.
- Adjusting the “4” height regarding to the flooring thickness, make sure the brusher at the right height.
- Adjusting the ”5” , make sure the flooring pass at the right direction, the gap between the floors as short as possible.
- Sensor “A”:The machine runs only when the sensor “A” is cover by the floors at the auto model .
- Suction opening(d=3 inch)is equipped on the dust remover which used for connecting the dust collection hose. dust collection machine is requested from the user side.
Glue Spreader
1.Digital display for the floor thickness 2. Hand wheel for anilox roller3. Glue tank 4. Anilox roller 5. Glue blade 6. Rubber supporting roller 7. Glue plate for cleaning
6.1 The glue spreader consists with anilox roller , rubber supporting roller and glue blade, the glue amount can be adjusted by the speed of the anilox roller and rubber roller. Hot melt glue is also available once the user equipped with mold temperature machine and glue melt machine. The rubber roller is specially designed with “FAST REPLACEMENT ”mechanical technology. Easy for the staff to replace the damaged rubber roller in very short time.
6.2 Adjusting the hand wheel to make the gap between anilox roller and supporting at the right position depends on the flooring thickness. The depth of parallelism of the anilox roller and rubber supporting roller need to be fixed after long- time operation by the coupling.
6.3 Keep the glue blade and anilox roller touched together, Adjust the glue baffle to touch closely to the anilox roller, make sure the glue not overflow when the anilox roller is turning. Lock the system.
6.4 Please clean the anilox roller when glue is still remained if the shift is off or long-time not using. Please make the ANILOX roller turn as slow as possible during the shift break, in case the glue gets aging.
6.5 Clean the anilox roller, glue blade as soon as possible after the operation. Turn the glue blade back, the glue drops down. Make the anilox roller up at the highest position, Put the glue plate between the anilox roller and rubber supporting roller. Close the glue blade , scatter the glue cleaner , switch the machine into the manual model. Make anilox roller turns slowly, keep clean several times. Make sure no remain glue on the anilox roller.
6.6 The method of using ANILOX roller is keeping the glue blade touched close, adjusting the glue baffle at the right position.
6.7 It is normal phenomena that glue leaks when the anilox roller is stopped. Adjust the glue baffle and blade when anilox roller is turning if it leaks.
Passing Belt
1.Rubber roller 2. Guide liner 3. Draught fan 4. Heater 5. Flexible conveyor 6.Sensor
7.1 Adjusting the “2” depends on the width, make “2” wider than the flooring width, turn on the belt conveyor, make the flooring right stop close with the “2”. The flooring is not allowed to be moved during the adjusting time. Move “2” slowly, little gap is requested to make sure the flooring pass well.
7.2 “4” consists with 3 metal heating pipe. The temperature can be adjusted by the controller. The temperature is normally set around 80 ℃.
7.3 The passing belt will not work when “5” is not rise at the right position.
7.4 Sensor B: It is used for controlling the end of the flooring which is under the laminating rollers, adjusting the Sensor B is able to control the position of the flooring which is under the laminating rollers.
7.5 Sensor C: It is used for controlling the head of the flooring which is not under the laminating rollers, also control the start-running of the flooring which is under the laminating rollers. Adjust the sensor c is able to adjust the gap between two floors( no less than 30mm at the beginning)
7.6 The gap of two floors can be adjusted by the sensor B & C. The user is also able to adjust the gap by the conveyor speed in case the Sensors are in the limited-position situation .
SPC FLOOR Automatic Back Pad Laminating Machine with Auto Cutting System
1.Small press roller 2. Passing roller 3. Servo cutter 4. Unwinder 5. Laminating rollers 6. Soft pad(IXPE) passing roller 7. Flexible roller 8. Soft pad(IXPE) position guide 9. Guide liner
8.1 Adjusting the “9” depends on the width, make “9” wider than the flooring width, turn on the belt conveyor, make the flooring right stop close with the “9”. The flooring is not allowed to be moved during the adjusting time. Move “9” slowly, little gap(1mm) is requested to make sure the flooring pass well.
8.2 Check the soft pad(IXPE) passing through drawing picture, put the IXPE roll on the unwinder, keep in the right position. Lock up. The unwinder can be turned in two directions depends on the IXPE roll’s warping direction.
8.3 Adjusting “3” &”5”, just touch the flooring and IXPE film. The gap is the thickness of the flooring and IXPE film. The gap needs to be adjusted during the operation. Make the pressure as much as possible unless glue over-flowed or pressure mark occurs.
8.4 Switch off the “3”, during the testing at the beginning. Feed the flooring one by one, watch the gap between two floorings is stable or not, also check the IXPE is at the right position or not. Move the auto cutter to the previous floor’s back side , distance 10mm.
8.5 Adjust “1” press the products.
8.6 Switch into the auto model when every procedures done. Pls move the products which are not trimmed in case the wastage.
8.7 Please press the triangle button showed on the picture before the IXPE roll is finished. Waiting for the IXPE runs out is also no problem, but the user may use knife to cut off the IXPE, and see the distance between the floors in case the floors get crashed together.
Passing Conveyor
1.Press roller 2. Belt
9.1. Adjusting the height of the press roller, laminating the IXPE film together with the flooring , make the glue stick stronger.
9.2. The belt is used for keeping the distance between floorings in case the floorings stay too close. The speed of the belt can be adjusted by the PLC.
Roller Conveyor
1.Rollers for passing 2. Chain tied/loose controller
10.1 The distance between the rollers can be adjusted depends on the flooring length. Just tie/loose the chain.
10.2 The purpose of speed adjusting is to make sure the flooring pass nicely and turn the direction to the trimming machine by sensor.
Trimming machine
1.Chain fixation 2. Flooring baffle 3. Movable chain 4. Cylinder for lifting the movable chain 5. Trimming cutter 6. Pathway for movable chain side 7.Supporting holder for flooring D. Proximity switch E. Proximity switch
11.1 Trimming machine consists with round cutter by high speed motor, the cutter can be adjusted according to the flooring groove.
11.2 The trimming machine can be adjusted by the length of the flooring, just lift the movable chain side by the cylinder.
11.3 Raise the “4” and move the “3” to adjusted machine working length depends on the flooring length.
11.4. Proximity switch D is designed to control the chain stop/start. When the flooring reaches the D, the chain will start to move, and push the flooring into the round cutters. Stopped by proximity switch E.
11.5 Proximity switch D is used to control the flooring from the belt conveyor in case the products broken issue occurred .
11.6 Proximity switch E is designed to control the position of the pushers on the chain. Keep the pushers stay with floorings as close as possible
Machine Pre- operation guide, main points.
Preparation and Checking.
12.1 Make the machine in the right position, adjust the screw under the machine to keep the machine in horizontal position. Adjust the anilox roller glue spreader’s horizontal position first then line the others parts.
12.2 Check the machine situation , tie the screw if some of them loosed.
12.3 Check the electrical wires from each machine parts to the electrical cabin. It is not allow to open the cabin by the untrained or not professional staff. Check the machine is running at the right direction or not.
12.4 Make sure the flooring is same size and thickness, also feed the floorings in the same direction.
12.5 It is not allow to touch or adjust the belt conveyor in case injury or scald issues occurred .
12.6 Maintenance is need monthly, fill up gear or mechanical oil is necessary.
Electric and Air Supply :
13.1 The total line is controlled by programmed PLC. Please take a note about the parameters in the PLC for different size of the flooring.
13 .2 Air supply: 0.4-0.8 MPA. It is suggested to use the air filters.